TEQIP Financial Status 2008
 


Financial Status of Programme Institutionas on 30th Sept., 2006

Category of Expenditure

Total Project Allocations

Cumulative Expenditure Up to 30.09.2006 since inception Committed Expenditure as on 30.09.2006* Expenditure in Pipeline as on 30.09.2006** Total
 (2+3+4)
Reimburse-ment Claimed out of Cumulative Exp.in Co.2 Balance Yet to be Claimed
 (2-6)
(1) (2) (3) (4) (5) (6) (7)
(I) INVESTMENT COST (Rs. in million)
Civil Works 19.00 - 18.933* - 18.933 - -
Equipment

127.00

49.431 33.435

24.260

107.126

49.431

-

Furniture 5.00 4.782

0.227

-

5.009 4.782 -
Vehicles 0.00 - - - - - -
Books & LRs

16.00

9.474 - -

9.474

9.474

-
Consultants services and research studies

2.00

0.020

- -

0.020

0.020

-

Training/Study Tours/Fellowships (Local and Foreign) / Workshops

13.00

 

4.033

 

1.066**

 

-

5.099

 

4.033

 

-
Total (I) 182.00

67.740

53.661

24.260 145.661

67.740

-

(II) INCREMENTAL OPERATIONG COST
Salaries for agreed Key Additional Faculty & Staff 18.00

0.095

- -

0.095

0.095

-
Consumables - 0.004 - -

0.004

0.004

-
Operation & Maintenance -

1.615

- -

1.615

1.615

-
Total (II)

18.00

1.714

- -

1.714

1.714

-

Sub total A (Total of I & II)

200.00

69.454

53.661

24.260 147.375

69.454

-

B. Networking of Institutions

8.00

0.557

- -

0.557

0.557

-
C. Services to Community & Economy

1.30

0.026

- -

0.026

0.026

-
GRAND TOTAL A+B+C 209.30

70.037

53.661

24.260 147.958

70.037

-
* Work started, money transferred **Advances given
.
Dr. Krishna Gopal,  Coordinator
Dr. Akhilesh Swarup, Co-coordinator.